Treasure Coast Food Bank
Timeline: May 2024 – July 2025
Description: 130,000 sf tilt building warehouse with full production kitchen, small kitchen, offices and warehouse/storage.
Scope: Draper provided both construction schedule development and construction monitoring services to Verdex Construction during all phases of the project. In addition, Draper conducted monthly update meetings during the construction phase, reviewing progress with the General Contractor and all active Subcontractors. Near Term Schedules, detailed day-to-day implementation schedules derived from the Overall Project Schedule, served as the focal point of discussion during the update meetings. A Primavera P6 schedule was utilized for Contract schedule tracking.