Time Impact Analysis (TIA)
Time Impact Analysis is the determination of a potential “forward looking” schedule impact. Typically completed when a differing site condition is encountered, or additional work is added to a project. Draper & Associates will assist in determining all the activities; design, procurement, and work that must be accomplished to complete the added/changed scope. Once the activities have been identified and time estimated to complete each activity is determined a “Fragnet or Subnetwork” is created. This “Fragnet or Subnetwork” of activities that is inserted into the current approved project schedule and the potential impact to the project is determined. This TIA can be utilized by the Owner and Contractor to negotiate a revised completion date. Draper & Associates is uniquely qualified utilizing its experience with hundreds of projects, by construction professionals to determine the potential impacts to projects.